Viridis Awards Water Recycling Package for Colossus

Proxa Australia will supply ultra-filtration and reverse osmosis equipment for the Brazilian rare earth project, the second major processing award for Colossus.

Updated on Nov. 17, 2026 in Corporate Finance

Viridis Awards Water Recycling Package for Colossus

Viridis Mining and Minerals has awarded a long-lead water and reagent recycling package to Proxa Australia for its Colossus rare earth project in Brazil. The contract is the second major processing equipment award for the project.

Why it matters

Recycling process water and ammonium sulphate reduces both operating costs and the need for fresh make-up water, which bears on the project's economics and water consumption. Viridis structured the commitment to limit its financial exposure before a final investment decision.

Viridis has committed US$0.88 million (A$1.3M) to engineering and design optimisation, with the balance of the package contingent on a final investment decision. The water recycling package has an anticipated delivery period of roughly 12 months, and the total contract value has not been disclosed.

The players

Viridis Mining and Minerals

Viridis Mining and Minerals is the developer of the Colossus rare earth project in Brazil, which it is advancing toward a planned five million tonnes per annum facility.

Proxa Australia

Proxa Australia is a process technology company that designed the water and reagent recycling system awarded for the Colossus project.

The details

The package incorporates ultra-filtration and reverse osmosis membrane separation technology to recover and recycle process water and ammonium sulphate. Proxa's process design has been integrated into Viridis' demonstration plant in Poços de Caldas, Brazil, and Viridis has selected Sedgman and Blossom as EPCM contractor.

Timeline

  1. September: Viridis reported a cash position of $120 million.

  2. 2028: Colossus project is targeting production start.

Market Dynamics

Rare earth developers are increasingly tying project economics to process water and reagent recovery, since reducing make-up water and reagent purchases lowers operating costs. Viridis' staged commitment, with most spending held back until a final investment decision, reflects how developers are managing capital exposure ahead of construction.

For shareholders, the staged commitment means most project spending remains contingent on a final investment decision rather than being locked in now. The outcome of that decision will determine whether the recycling package and the wider Colossus build proceed on the targeted 2028 schedule.

The takeaway

Recycling process water and reagents is becoming a core cost lever for rare earth projects, and staged contract commitments can limit financial exposure before final investment decisions.