DPM Targets Higher End of 2026 Gold Output

The miner delivered 95,917 gold equivalent ounces in the third quarter as its Vareš mine reached commercial production.

Updated on Nov. 13, 2026 in Economic Indicators

Wide view of a steel headframe and concrete processing plant on a terraced hillside, with a conveyor belt running down toward a settling pond under overcast sky.
DPM said its Vareš mine reached commercial production ahead of schedule in August and expects to exceed the high end of its 2026 gold output guidance. AI Illustration. Upload story photo >

DPM expects to reach the higher end of its 2026 gold equivalent ounce production guidance and to land in line with its all-in sustaining cost guidance. The company delivered 95,917 gold equivalent ounces in the third quarter of 2026.

Why it matters

Higher production paired with a rising realised price points to stronger output economics for the company, while an 8% year-on-year rise in AISC shows cost pressure is also building. Investors and communities across the region will watch whether the Vareš ramp-up and Serbian project timelines hold.

DPM reported 95,917 gold equivalent ounces in the third quarter of 2026, with AISC of $1,580/oz (up 8% year-on-year) and a realised price of $4,313/oz (up 18%). Timing and cost effects of the Serbian regulatory changes remain unquantified.

The players

DPM

DPM is a mining company with operations in Bulgaria, Bosnia and Serbia, and it acquired the Vareš mine from Adriatic Metals last year.

Zijin Copper

Zijin Copper is a subsidiary of China's Zijin Mining Group whose expansion plans at Jama Bor in Serbia are the subject of calls for suspension.

The details

DPM said Vareš achieved commercial production ahead of schedule in August and is expected to exceed the high end of its production guidance. The company also raised its exploration expense guidance to $75 million to $80 million, reflecting positive results to date, and expects to complete an initial Mineral Resource estimate for the Wedge Zone target at Chelopech by year-end.

Timeline

  1. August 2026: Vareš achieves commercial production ahead of schedule.

  2. Third quarter 2026: DPM delivers 95,917 gold equivalent ounces.

  3. November 2026: A change in the Serbian government takes place.

  4. Year-end 2026: Vareš is expected to reach an 850,000 tonne per year run-rate, and the Wedge Zone resource estimate is due.

Market Dynamics

DPM's 18% year-on-year rise in realised gold price during the third quarter of 2026 is the clearest sign in this update of how the 2026 gold price cycle is feeding through to producer revenue. That price strength is being partly offset by an 8% rise in AISC, so margin gains are narrower than the price move alone would suggest.

For readers tracking gold prices and mining equities, the higher realised price and rising costs in this report show how producer margins move with the metal price and input costs. Investors with exposure to gold producers can use the stated AISC guidance range as a benchmark when comparing quarterly results.

The takeaway

Quarterly production and cost data are the most direct gauge of how a miner is converting higher metal prices into margin. Comparing reported AISC against published guidance over successive quarters shows whether cost pressure is temporary or structural.

What happens next

DPM expects to complete an initial Mineral Resource estimate for the Wedge Zone target at Chelopech by year-end 2026, and Vareš is on track to reach an 850,000 tonne per year run-rate by the same date.

Further reading

For broader context on the metrics behind this report, explore Economic Indicators.

Source note: This article includes information reported by Mining-journal.