Panel Urges Risk Sharing to Scale Carbon Capture
Speakers at COP31 in Antalya, Türkiye, said carbon capture and storage needs shared risk, capture-side incentives and green lead markets to grow.
Updated on Nov. 11, 2026 in Business Strategy

At a Nordic Pavilion panel at COP31 in Antalya, Türkiye, representatives from Heidelberg Materials, the Global CCS Institute and energy officials from Norway and Brazil discussed how to scale carbon capture and storage. Heidelberg Materials' Brevik initiative is set to become the world's first full-scale carbon capture plant at a cement facility.
Why it matters
Cement is an emissions-intensive industry, and a full-scale capture plant at one facility would test whether the technology can be deployed commercially. The panel's emphasis on risk sharing and incentives reflects the financing hurdles that have slowed similar projects.
The Brevik initiative is projected to capture 400,000 metric tons of CO2 annually, half of the plant's emissions. Construction timing and total investment were not disclosed in the source material.
The players
Heidelberg Materials
A major international building materials company whose Brevik initiative aims to be the first full-scale carbon capture plant at a cement facility.
Global CCS Institute
An international think tank that promotes the deployment of carbon capture and storage technologies worldwide.
The details
Brevik CCS partners with the Northern Lights transport and storage project, which moves captured CO2 by specialized ship to subsea offshore storage. Norway's carbon capture leadership traces to the 1996 Sleipner offshore project and now extends to the Longship initiative, and the CCS Brazil Association is drawing on that support to shape country-specific regulatory frameworks and MRV standards.
Timeline
1996: Sleipner offshore CCS project begins in Norway.
November 11, 2026: Nordic Pavilion panel on carbon capture held at COP31 in Antalya, Türkiye.
Business Strategy Context
The Brevik project extends the offshore storage model Norway began at Sleipner in 1996 into cement, a sector where capture has been hard to finance. Its success would show whether the Northern Lights network can serve industrial emitters beyond Norway.
Carbon capture costs tend to feed into the prices of cement and construction materials over time, so financing decisions made now could eventually affect project budgets. Companies and investors tracking industrial decarbonization will watch whether public-private risk sharing becomes standard practice.
The takeaway
Scaling carbon capture depends less on the technology itself than on who bears early financial risk. Watch for risk-sharing and capture-side incentive models as signals of which industrial projects reach operation.
Further reading
For related corporate planning, see Business Strategy coverage of how companies position long-term industrial investments.