Techouse secured a contract from Black & Veatch to supply two heat recovery steam generator (HRSG) modules, each weighing approximately 1,000 tonnes, for Golar LNG's fourth floating liquefied natural gas (FLNG) project. The announcement follows Golar LNG's agreement to acquire the LNG carrier Grace Dahlia from NYK Line for conversion into the unit.
Why it matters
The HRSG technology recovers heat from gas turbine exhaust to generate steam for electricity and LNG processing, and the system is projected to cut fuel consumption by 20-25% versus gas-turbine-only setups. The contract extends Techouse's prior HRSG work on the FLNG Gimi and FLNG Esperanza projects.
The projected 20-25% fuel consumption reduction is measured against conventional gas turbine-only systems, per the company's announcement. The two HRSG modules weigh roughly 1,000 tonnes each, and the financial value of the contract was not disclosed.
The players
Techouse
A Norway-based engineering company that supplies heat recovery steam generator technology for floating LNG projects, having previously supplied the FLNG Gimi and FLNG Esperanza.
Golar LNG
An LNG shipping and floating liquefaction company that is converting the Grace Dahlia into its fourth FLNG unit.
Black & Veatch
An international engineering and consulting firm that is responsible for the FLNG topside solutions and awarded the HRSG subcontract to Techouse.
The details
Techouse will deliver the equipment as a subcontractor to Black & Veatch, which is responsible for FLNG topside solutions, with engineering and procurement managed from Techouse's offices in Norway. Partner Alpha ECC will manufacture the units in Vung Tau City, Vietnam, before shipment to Himile Heavy Industries in China for assembly into complete HRSG modules, and work has started immediately.
Timeline
October 7, 2026: Golar LNG announced its agreement to acquire the Grace Dahlia.
November 10, 2026: Techouse announced the HRSG contract.
End of 2028: Delivery of the HRSG modules is planned.
2029: Final redelivery of the converted FLNG unit is targeted.
Market Landscape
Techouse's HRSG supply role on FLNG Gimi and FLNG Esperanza is carried forward into Golar LNG's fourth FLNG unit, reinforcing its position as a specialist supplier of waste-heat recovery systems for floating LNG facilities. The expansion of floating LNG capacity places HRSG suppliers in a niche where fuel-efficiency claims become a competitive differentiator.
For readers following energy costs, the projected 20-25% fuel reduction is a claim tied to LNG production efficiency rather than a consumer-facing price change. The stub provides no direct effect on retail energy prices or supply availability for households.
The takeaway
Efficiency gains from waste-heat recovery are becoming a central selling point in floating LNG, where fuel use drives operating economics. Watching whether the projected fuel savings are realized at delivery will show how these systems perform in practice.