ECOWAS Reports Delays on Cavally Bridge
High water and logistical problems are slowing work on the bridge linking Côte d'Ivoire and Liberia.
Updated on Nov. 1, 2026 in Current Conditions

Live Poll
Do you trust large government infrastructure projects in your country to finish on schedule?
ECOWAS reported that high water levels, ferry difficulties, and problems drilling riverbed piles are hampering construction of the Cavally River bridge on the Ivorian side. The planned 288-metre, two-lane bridge is intended to connect Côte d'Ivoire and Liberia.
Why it matters
The bridge is meant to link two neighboring West African countries, so delays affect cross-border connectivity. The update did not announce an opening date.
The 288-metre, two-lane bridge was handed to the contractor on October 3, 2024, and an ECOWAS inspection on October 28 found progress on the Liberian bank but material movement still constrained on the Ivorian side. The update gave no completion or opening date, and the contractor's proposed support measures are not due until the end of November.
The players
ECOWAS
The Economic Community of West African States is a regional bloc that oversees the Cavally River bridge project and issued the construction update.
Khare Diouf
Diouf is ECOWAS's resident representative who inspected the bridge construction site at Prollo on October 28.
Prefect of Tabou
The prefect is the local Ivorian administrative official who asked the contractor to present measures to keep construction moving.
The details
ECOWAS resident representative Khare Diouf visited the Prollo construction site on October 28 and inspected both banks of the river. The prefect of Tabou asked the contractor to present support measures, including a temporary bridge, by the end of November, while CI-Énergies has completed cabling and electricity supply is planned for the first week of November.
Timeline
October 3, 2024: ECOWAS handed the site to the contractor and supervising consultant.
October 28, 2026: ECOWAS representative inspected the Prollo construction site.
November 1, 2026: ECOWAS issued its update on construction obstacles.
First week of November 2026: Electricity supply is planned for the bridge site.
End of November 2026: The contractor is due to present support measures to the prefect of Tabou.
Seasonal Patterns
The Cavally bridge's high-water delays arrive in the rainy season, when river levels on the Côte d'Ivoire–Liberia border frequently rise and disrupt riverbed work. The delay fits a recurring pattern on ECOWAS cross-border projects, where construction schedules are repeatedly tested by wet-season water levels.
Travelers and residents who rely on crossing the Cavally River should not plan on the new bridge being open yet, since no opening date has been announced. Those who must cross in the meantime should expect ferry difficulties and high water to continue affecting movement.
The takeaway
Large cross-border projects can stall on local conditions such as high water and material movement, so timelines announced at handover may shift. Watch for the contractor's support measures due at the end of November.
What happens next
The contractor is due to present support measures, including a possible temporary bridge, to the prefect of Tabou by the end of November 2026.
Further reading
For ongoing updates on conditions affecting the region, see Current Conditions.
Source note: This article includes information reported by Okay News.