Citaglobal Subsidiary Won Waste-to-Energy Project Contract
The firm secured a contract in Thailand to build a waste-to-energy plant in Nakhon Ratchasima Province.
Updated on Oct. 5, 2026 in Construction

Live Poll
Do you believe international waste-to-energy projects are a positive development for host countries?
Citaglobal subsidiary LAWI Engineering GmbH has won a RM29 million contract for a waste-to-energy project in Thailand. The initiative is part of a larger RM52.1 million consortium contract to construct a new steam boiler plant.
Why it matters
The project aims to process 500 tonnes of municipal solid waste daily while generating 9.9 megawatts of electricity. This development marks a significant expansion for the firm in the regional sustainable energy sector.
The awarded contract is valued at RM29 million, contributing to a total project consortium deal of RM52.1 million. The facility is expected to handle 500 tonnes of waste daily and produce 9.9 megawatts of power.
The players
Citaglobal
This is a diversified Malaysian conglomerate that holds a majority stake in the environmental management division involved in the contract.
LAWI Engineering GmbH
This company is a subsidiary of Citaglobal that specializes in engineering solutions for waste-to-energy power facilities.
The details
LAWI Engineering GmbH, which is 55% owned by Citaglobal Environment Management, will handle construction of the steam boiler plant and basic engineering. The project is situated in Nakhon Ratchasima Province and utilizes a consortium model with a partner to complete the work.
Timeline
The boiler island is expected to begin commercial operations within 13 months of the contract award.
Market Landscape
This project aligns with the broader regional shift toward waste-to-energy infrastructure as a solution for urban waste management. The deal positions the company to capture market share in Southeast Asia by combining specialized engineering with utility-scale power production.
Local communities in Nakhon Ratchasima Province may see long-term benefits from improved waste processing capabilities and increased power capacity. However, there are no immediate changes to individual consumer utility pricing or household services as a result of this initial construction award.
The takeaway
Waste-to-energy projects require specialized engineering consortiums to manage both industrial waste and electrical output requirements. Investors should monitor the 13-month timeline as a benchmark for the operational viability of these complex infrastructure developments.